What is schedule variance in software testing?

Schedule variance is basically used to indicate whether a project is running ahead or behind. It is the difference of Budgeted Cost of Work Performed (BCWP) and Budgeted Cost of Work Scheduled (BCWS). Schedule variance is computed by calculating the difference between Earned Value and Planned Value.

What is schedule variance?

Schedule variance is an indicator of whether a project schedule is ahead or behind. It is typically used within earned value management (EVM) to provide a progress update for project managers at the point of analysis.

What causes schedule variance?

Schedule Variance (usually abbreviated as SV) is an indicator of whether a project schedule is ahead or behind. It’s typically used within Earned Value Management (EVM). Schedule Variance can be calculated by subtracting the Budgeted Cost of Work Scheduled (BCWS) from the Budgeted Cost of Work Performed (BCWP).

What is the difference between cost and schedule variance?

Cost variance is the difference of earned value and actual cost. Schedule variance is the difference of earned value and planned value. If cost variance is negative then the project is over budget.

How do you calculate project schedule variance?

To calculate SV, subtract your project’s planned value (PV) from its earned value (EV): SV = EV – PV. You will also need to know the value of your project’s planned budget at completion (BAC). If your SV is positive, your project is ahead of schedule. If it is negative, your project is behind schedule.

What does a schedule variance of 0 mean?

A positive schedule variance (SV > 0) indicates that the earned value exceeds the planned value in the reference period(s), i.e. the project is ahead of the schedule. If the schedule variance is 0 this indicates that that the schedule baseline is met, i.e. the earned value is equal to the planned value.

How is schedule variance index calculated?

The schedule variance, SV, is a measure of the conformance of the actual progress to the planned progress: SV = EV – PV.

What is the EAC formula?

Estimate at completion (EAC) is calculated as budget at completion divided by cost performance index. Formula 1 for EAC is as follows: Estimate at completion (EAC) = Budget at completion (BAC) / Cost performance index (CPI)

What is SPI PMP?

“The Schedule Performance Index (SPI) is a measure of schedule efficiency, expressed as the ratio of earned value to planned value.” At the core, the SPI gives insight into the accuracy of the predicted schedule compared to the actual schedule of the project.

How do you calculate SV and CV?

– Cost Variance (CV): The CV is the difference between the earned value of the work performed and the executed budget (Actual Cost). CV= EV-AC. – Schedule Variance (SV): The SV is the difference between the earned value of the work performed and the planned value of the work scheduled. SV= EV-PV.

What is EV and AC?

Actual Cost (AC) = actual costs to date. Earned Value (EV) = total project budget multiplied by the % of project completion.

What does it mean if CV is positive and SV is negative?

SV is positive and CV is negative: The project is ahead of schedule but over budget. In other words, more tasks have been performed than were scheduled at this point, but the tasks that have been performed are over budget. SV is negative and CV is positive: The project is under budget but behind schedule.